Fukushima Workers Made to Falsify Radiation Exposure — Covered Dosimeters with Lead Plates

From the Boston Globe, article by Mari Yamaguchi, July 23, 2012.

Japanese authorities are investigating subcontractors on suspicion that they forced workers at the tsunami-hit nuclear plant to underreport the amount of radiation they were exposed to so they could stay on the job longer.

Labor officials said Sunday that an investigation had begun over the weekend after media reports of a coverup at the Fukushima Daiichi plant, which had multiple meltdowns following the March 2011 earthquake and tsunami disasters.

A subcontractor of plant operator Tokyo Electric Power Co., or TEPCO, acknowledged having nine workers cover their dosimeters with lead plates late last year so the instrument would indicate a lower level of radiation exposure.

The investigation marks the first time the government has looked into the case, believed to be part of a widespread practice at the plant since it was hit by the worst atomic crisis since Chernobyl.

The government more than doubled the emergency radiation exposure limit soon after the accident, but lowered it back to the previous level in December.

The law now sets the exposure limit at 50 millisieverts per year, or a five-year total of 100 millisieverts.

Dosimeter readings are crucial personal records that determine how much longer a worker can stay on a plant job. Work at highly contaminated areas could quickly eat up a worker’s quota.

The issue reflects a growing concern among the government and TEPCO about how to secure a continuous flow of workers to finish cleaning up the plant. Officials say it will take about 40 years to decommission the plant’s four wrecked reactors — three with melted cores and another with a spent fuel pool in a shattered building.

Labor officials made onsite inspections at the Fukushima plant to examine dosimeter readings of the workers and other records, said Yasuhiro Kishi, an official at the Fukushima Labor Bureau.

Health and Labor Ministry officials repeatedly issued warnings to TEPCO during the first few months of the crisis about the company’s lax oversight of workers’ exposures.

Officials have also said TEPCO had several workers share a dosimeter not just early in the crisis when the equipment was in short supply due to tsunami damage, but even after a full stock had been regained.

Takashi Wada, president of Fukushima-based subcontractor Build-Up, acknowledged this weekend that the dosimeter falsification had taken place. He said a supervisor of the group of nine workers came up with the idea when his dosimeter alarm went off during his short preview visit to the area where the workers were assigned.

‘‘We should have never done that,’’ Wada told an interview with TBS network broadcast Saturday.

A study released this month concluded that radiation from the Fukushima nuclear plant may cause as many as 1,300 cancer deaths globally.

The March 2011 nuclear disaster may cause as many as 2,500 cases of cancer, mostly in Japan, according to the study by scientists at Stanford University.

They incorporated emission estimates into a global atmospheric model to predict the effects of radiation exposure, which was detected as far away as the United States and Europe.

Cancer cases may have been at least 10 times greater if the radiation hadn’t mostly fallen in the sea, said Mark Jacobson, coauthor of the study, the first detailed analysis of the event’s global health effects.

Advertisements
This entry was posted in Energy, Fukushima, Global Fallout, Issues, Monitoring, Nuclear, Other Power Plants, Radiation Information, Safety, Sampling. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s